The oceans have been around for roughly 4.5 billion years. They cover 70 per cent of the planet, but we have yet to explore 95 per cent of their depths. In a bid to further investigate the wonders of the deep, scientists have recently researched mining rare metals — such as copper, zinc and gold — from volcanic rock on the seabed.
When a winch controlling a high-powered drill broke down on a
ship mining samples off the coast of Japan, costing the company over $30,000 a
day, the crew called maintenance and repair specialist
CP Automation. Here, global business development manager John Mitchell
discusses how CP Automation got the application running smoothly under strict time
constraints.
Due
to the location of the mineral rich area off the coast of Japan, sample
extraction has to be planned 20 hours in advance, in accordance with how high
wave crests were. The rougher the waves, the more the drill moves and the
higher the risk of damage to an incredibly expensive piece of equipment.
Just
before the company deployed the drill for the first time, faults with the winch
began to appear. Onboard engineers found the problem to be a DC BUS overvoltage
issue caused by the brake chopper. The engineers attempted to alleviate the
problem by replacing the brake chopper like-for-like, but their attempts proved
unsuccessful.
After
calling a representative from the brake chopper manufacturer, they agreed to
fly out as soon as possible. Unfortunately, due to time constraints, this
meeting was cancelled, leaving the project losing tens of thousands of dollars
every day and those on board no closer to rectifying the problem.
By
the time the company contacted CP Automation, the drill had been out of action
for two weeks and the crew were at wits' end.
Winch and drill
The
winch system controls the deployment of the drill to the seabed, which could be
up to 3km from the ship. The winch also provides under tension — keeping the
cable taught during payout. The brake chopper unit, rated at 400KW continuous
600A and 600KW, 900A at peak, dissipates the excess DC BUS voltage fed back from
the motor.
If
the winch cannot dump the energy created during this process into the braking
resistors because the brake chopper has a fault, then the operator can't
control the cable. This would result in the loss of a drill worth millions of
pounds. It was therefore imperative that the brake chopper was reliable before
the crew deployed the drill.
Once
the drill is in the water, the application provides active heave, compensating
for the wave movement by automatically driving the winch in the opposite
direction at the same speed to stabilise the drill. The drill has to remain at a constant height
from the sea floor so that it can clamp in position.
Getting on board
Because
time was of the essence, CP Automation flew out to Japan as soon as we could. We
powered up the application when the boat was docked and the brake chopper
exhibited new sets of faults each time we tested. It was difficult to test
under working conditions because we were unable to deploy the drill, which
would work the winch motors. It was therefore impossible to tell if there were
any electrical noise problems, which was our suspicion.
CP
Automation removed the existing brake chopper and fitted its own 100KW unit
into the system. The fault did not transfer to our product, but reoccurred when
we reinstalled the old unit.
Because
the ship's crew identified a window when the sea would be calm enough to live
test the drill, we were unable to carry out any more tests in dock.
Pushing off
The
new brake choppers CP Automation installed were each a quarter the rating of
the original unit. Consequently, we had to limit the max speed of the winch until
it was possible to assess the current required during payout and active heave.
To
fit the two brake choppers, we had to modify the control panel. This required
us to split the DC BUS into two, with drives one and two on DC BUS one and
drives three and four on BUS two.
This
provided the system with an element of redundancy it did not have before. There
was now the option that, should anything go wrong, the crew could operate the
system with only two of the four drives.
After
more tests in mild waves of 1.4m in height, the brake choppers were pulling 30A
max per unit during active heave when the drill was at 750m from the ship. The
DC bus level was maintained below 750VDC the whole time, which proved that the
replacements were a proficient fix.
The
client deployed the drill five times throughout the twelve hours and the system
ran smoothly every time. As far as we could tell, there were no more issues relating
to the brake choppers and the crew were able to extract all the mineral samples
necessary.
A shore fix
After
careful testing, we proved that CP Automation's brake choppers worked in the drill
application because, unlike the original unit, our brake choppers did not use
external power controls. This meant they are not susceptible to external noise.
The previous brake chopper had no electromagnetic compatibility (EMC) or
harmonic filter installed, so the resultant electrical noise from the drill
application and those around it, caused the brake chopper to fault.
Scientists, fiction writers
and film directors often refer to the oceans as the last frontier because of
just how little we know about their depths. Indeed, deep-sea mining is still
only in its infancy; scientists predict that minerals could be in abundance
under our unexplored seas, albeit difficult to extract.
The drilling project CP
Automation managed to revive is one of the first of its kind to sample valuable
metals from tough volcanic rock. With the help of more research and investment,
this method of mining could lead to a healthy flow of essential resources for
years to come.
No comments:
Post a Comment